Mumbai-Goa highway remains unfinished years after deadline, costs surge by ₹5,500 crore
- 8 kilometres across five Mumbai-Goa highway stretches remain unfinished, years after their original completion deadlines.
- Cost estimates for Maharashtra's highway section rose 44%, from ₹12,532 crore to over ₹18,100 crore.
- Delays stem from contractor financial troubles, land acquisition hurdles, clearances and local protests, officials said.
- Ministry says remaining work will finish by April 2027; the highway is already 99% complete.
Source: indianexpress.com